USD $4,127.96
First gold pour achieved within 12 months as ramp-up progresses
Meeka Metals Limited (ASX:MEK) has poured first gold at its Murchison Gold Project on schedule, marking production within 12 months of breaking ground.
Key points from the announcement include:
- First gold poured on schedule within 12 months at Murchison.
- Gold production ramping up smoothly, aligned with operational targets.
- Ore stocks building in front of the processing plant, following arrival of the third dig fleet in June 2025.
Meeka’s Managing Director Tim Davidson said:
It is an impressive achievement by the team to deliver first gold on time and within 12 months of breaking ground at the Murchison. We are now focussed on ramping up gold production toward our targeted 80koz per annum with the arrival of the third dig fleet and expanded open pit mining plan underway, and first ore from underground at Andy Well in the September 2025 quarter.

